Calgary's work to build a replacement water main, after two catastrophic breaks in recent years, is now complete. The city announced on Thursday the new Bearspaw feeder main is fully built and connected to the water system, after work began in January on the p
Illustrative imageCalgary's work to build a replacement water main, after two catastrophic breaks in recent years, is now complete.
The city announced on Thursday the new Bearspaw feeder main is fully built and connected to the water system, after work began in January on the project. The city said it expects to lift ongoing water restrictions next week.
After a second catastrophic break in the city's key water main occurred at the end of last year, Mayor Jeromy Farkas ordered construction of a replacement pipe to be fast-tracked and completed by the end of 2026.
"We accomplished in less than 11 months what many thought would take four years or more," said Farkas on Thursday.
The pipe will now be pressure tested, cleaned, flushed and refilled to pass water quality testing. The city said it expects the new pipe to be operational next month.
In the meantime, the city will refill the old Bearspaw feeder main, which it expects to take about five days. Once the pipe is full, the city will test water quality in the old pipe and check the system, before opening valves and starting pumps at the Bearspaw Water Treatment Plant.
In the meantime, Stage 4 restrictions remain for Calgary and neighbouring communities that rely on its water system like Airdrie, Chestermere, Strathmore and Tsuut'ina Nation. The current round of restrictions has been in place since Nov. 4.
After the success of the Bearspaw project this year, Farkas highlighted a need for the city to bring the same effort and urgency to bolster its infrastructure deficit overall.
"We cannot spend the next decade responding to emergencies that we have the power to prevent today," said Farkas.
"We must build infrastructure ahead of growth. We must replace aging infrastructure before it fails. We must build enough capacity to withstand emergencies and a changing climate."